The following table gives the activities in a construction project and other relevant information:

Activity

1 - 2

1 - 3

2 - 3

2 - 4

3 - 4

4 - 5

Duration

20

25

10

12

6

10

          Required:

  • Draw the network for the project.                                                                          [ 5 marks ]
  • Find the critical path                                                                                              [ 3 marks ]
  • Find free, total and independent floats for each activity.                                            [ 2 marks ]

 